Article summary: A revised drawing and a “received” reply leave the pric…
If window drawings change after quotation, ask for an explicit response against the affected quotation items before instructing production. For a Singapore project team buying custom sliding windows, the immediate question is whether the priced scope still describes the revised requirement. A reply saying “received” acknowledges a file; it leaves that question unanswered.
Imagine a revised elevation arriving while procurement is preparing an order. One opening changes, while the rest appear untouched. The architect, supplier and site team may each understand the drawing, yet still be waiting for different decisions. A useful exchange makes those decisions visible.
Tie the question to the quoted item
Send the revision with the quotation reference and identify the item you want reviewed. Describe the difference between the drawing used for pricing and the current proposal. If one quoted line covers several openings but only some have changed, ask the supplier to distinguish the affected portion from the remainder.
A concise note might say: “This revision changes the opening arrangement covered by this quotation item. Please confirm which parts of the quoted scope remain applicable and which need a new response.” Include both drawing references so the recipient can compare them without guessing which attachment you mean.
Ask for a response that names the difference
For each affected item, ask the supplier to state whether it remains covered as quoted, needs a revised price or scope, or still requires clarification. A revised total on its own can be difficult to interpret. Request the assumptions, inclusions and exclusions behind that response.
If sliding window sizes have changed, for example, ask what the supplier needs to reconfirm for that item. Let the responsible parties assess the proposed configuration. Do not turn a drawing note into your own conclusion about price, production timing or technical suitability.
When the reply is incomplete, return a specific question: “The quantity has been addressed, but the revised configuration has not. Is your response based on the new drawing?” That gives the recipient something concrete to resolve instead of another general request to check the package.

Reconnect samples and site interfaces
A finish or glass sample may have been reviewed before the latest drawing arrived. Ask whether it still represents the proposed supply, and who will confirm that relationship. If a replacement sample is needed, name that outstanding decision rather than leaving the previous sample in circulation without explanation.
Send any changed interfaces to the people coordinating the adjoining work. The site team may need to review wall finishes, nearby fittings or installation access. Ask each relevant party to identify what changes for their scope and which information they still need. This is a request for review, not an instruction to improvise a detail.
Separate the review from a production instruction
A design comment, a pricing response and an instruction to manufacture have different purposes. Agree who consolidates them for this package and who gives the confirmed production instruction. That person needs to see the unresolved differences as well as the accepted ones.
If part of the package is ready while another item remains open, ask the supplier whether a separate release is workable. Identify exactly which items are included. A message approving “the latest drawings” can leave people uncertain about an unresolved quotation line.
Our mixed-use window schedule guide explains the wider opening record. For this particular exchange, close with a response that connects the current drawing, the applicable quotation and the relevant sample decisions. Send it back to the people who raised the changes, so the next instruction has a shared, specific basis.